Notice
Coming Soon
May 16, 2012 - the trenches have been filled in. Next week we start putting up drywall and assembling the walk-in cooler - things should start progressing rapidly from here on in!
May 4, 2012 - waiting to get the plumbing inspected!
Friday the 13th 2012 - demolition begins!
We are making tremendous progress!
We received approval of our Federal Brewers Permit on April 5th, 2012. This was quickly followed up the next day with the city of Pinellas Park approving our building plans! We are ready to roll!
The city of Pinellas Park has granted a Conditional Use permit for a 'Brewery with tasting room' for the location we have selected!
We signed the lease on a 3,200 sq. ft. facility located in the heart of Pinellas county on December 16, 2011!
We filed our Brewer's Notice with the Federal Government (TTB) on December 16, 2011!
We received the key on Thursday - December 29th 2011!
The Power has been turned on - January 2, 2012!
The Rapp Brewery officially has a home and its not in the Rapp home back yard anymore!!
A Contractor has been selected and building plans have been prepared and were delivered to the City of Pinellas Park on February 15, 2012!